stuntpenguin007
Member
6/22/11
I got the expansion pack relocated. I'm surprised that it actually worked. It took me about 3 - 4 hours total to do. The last half hour was mostly troubleshooting and looking for shorts.
I also got the cartridge slot relocated. I was a little bit scared when it didn't boot at first, but I later found out that the power supply I was using was semi-faulty. It works sometimes and not others. So I used a different power supply and it worked.
6/23/11
I found something at a thrift store today that looked like it would work good as a case. It's a little bit bulky, but it seems like it would make a comfortable portable. So I went to work on it. I have the screen area dremeled out so far. I'm going to save the ZN-40 for a different project.
6/24/11
Got the space for the A, B, C-Buttons, and thumbstick cut out. Right now I'm waiting for the ABS cement to dry.
I got the expansion pack relocated. I'm surprised that it actually worked. It took me about 3 - 4 hours total to do. The last half hour was mostly troubleshooting and looking for shorts.
I also got the cartridge slot relocated. I was a little bit scared when it didn't boot at first, but I later found out that the power supply I was using was semi-faulty. It works sometimes and not others. So I used a different power supply and it worked.
6/23/11
I found something at a thrift store today that looked like it would work good as a case. It's a little bit bulky, but it seems like it would make a comfortable portable. So I went to work on it. I have the screen area dremeled out so far. I'm going to save the ZN-40 for a different project.
6/24/11
Got the space for the A, B, C-Buttons, and thumbstick cut out. Right now I'm waiting for the ABS cement to dry.